Master Programme Vs Target Programme
In the Open Standard
KS WongMember for 19 years
- Created
- 4
- 2
0
Dear Planners,
In order to avoid being criticized for slow progress in progress meetings, main contractor would submit a Master Programme with late scheduled dates or excessive contingency time at the front of the project.
For controlling their subcontractors, a target programme with more realistic / aggressive dates will be adopted for their internal management.
I would like to seek your comments on the above arrangement. Is this a common practice to your project? Would it cause any other management problems? Thanks.
Regards,
KS
In order to avoid being criticized for slow progress in progress meetings, main contractor would submit a Master Programme with late scheduled dates or excessive contingency time at the front of the project.
For controlling their subcontractors, a target programme with more realistic / aggressive dates will be adopted for their internal management.
I would like to seek your comments on the above arrangement. Is this a common practice to your project? Would it cause any other management problems? Thanks.
Regards,
KS
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?