Dear All,

Can any one send me the program sequence for the Irrigation Steel Water Tank.(for L4 Schedule).


Thanks & Regards,

Anbin Ponnith

7 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Anbin,

    The following activities will help you with Building your schedule:

    Site Activiites:
    I. Substructure
    Excavation
    Blinding
    Shuttering of Raft
    Reinforcement of Raft
    Anchor Bolt Setting
    Casting of Raft

    II. Super Structure
    Erection of Steel Base
    Welding of Plates (Level 1, 2, 3, etc)
    Testing of Welds
    Mechanical Fittings
    Testing of Mechnical Fitting.
    Electtrical installation.
    Painting of Structure.
    Installation of circulat ladders and handrails

    III. Roof Installation
    Scafolding or Lifting depending on the type of Roof.
    Installation of circulat ladders and handrails
    Testing of Welding
    Painting

    It would be highly recommended that you read the specifications, BOQs and Plans and include all the scope of work that you have in the Schedule of Work. Come up with a draft and show it to your team members, they will correct it and update you with the correct activities and sequence of works.

    With kind regards,

    Samer
  2. 0
    Anbin Ponnith ·
    Thanks Samer,

    I have to submit the initial program to the client,

    I have prepared in this way,
    Irrigation Water Storage Tank 58 m Dia.

    I.Sub Structure
    Excavation & Compaction
    ATT & Vapor Barrier
    Blinding
    Footing Rebar & Shuttering
    Pour for Footing
    Ring wall Rebar & Shuttering
    Pour for Ring Wall
    Water proofing
    Backfilling
    Cathode Ribbon & Conductor Bars
    II.Super Structure
    Laying of Bottom plate
    Erection of Structural Columns
    Erection of Girders
    Erection of Rafters
    Erection of Shell
    Erection of Roof
    III.Finishers
    Erection of Staircase & ladder
    Fixing of Nozzles
    Cathodic Protection
    Fixing of Accessories
    Painting.

    Please give me comments,

    With Thanks & Regards,

    Anbin Ponnith
  3. 0
    Samer Zawaydeh ·
    Dear Anbin,

    This is a good start.
    Please add the following at the start of the program:

    1. Material submittals.
    2. Shop drawings submittals.
    3. Method Statements
    Safety Plan
    Erection Plan
    4. Quality Records
    Inspection and Testing Plan
    Certification of Welders
    Welding Procedures
    5. Procurement: you need to mention the arrival of material at site.
    6. At the end of the program you need to mention the Testing and Commissioning and Handing over to client.
    A. "As Built" drawings
    B. Quality Manual; inspection records, MTCs, Welding Maps, Test results.

    7. Please show the installation of the Achor Bolts as an independent activity, because it will be handed over to client.
    8. Have a look at the Electromechancial requirements of the project and make sure that you include them all.
    9. Check the inspection requirements at site and include then in yoru construction sequence.
    10. Check what is the height of the tank and how many plates you have and show them as levels in your construction sequence.

    With kind regards,

    Samer
  4. 0
    Anbin Ponnith ·
    Dear Samer,

    Thanks a lot.I have submitted the program with all ur suggesions and remarks,,


    With Thanks & Regards,

    Anbin Ponnith
  5. 0
    Samer Zawaydeh ·
    Dear Anbin,

    Please provide a copy to your construction team as well. You need to talk to them about the details and the sequence of work. They will have to build it for your. So, their opinion is a major criteria in the successful achievement of the Program of Works.

    With kind regards,

    Samer
  6. 0
    Samer Zawaydeh ·
    Dear Anbin,

    Please provide a copy to your construction team as well. You need to talk to them about the details and the sequence of work. They will have to build it for your. So, their opinion is a major criteria in the successful achievement of the Program of Works.

    With kind regards,

    Samer
  7. 0
    Samer Zawaydeh ·
    Dear Anbin,

    Please provide a copy to your construction team as well. You need to talk to them about the details and the sequence of work. They will have to build it for your. So, their opinion is a major criteria in the successful achievement of the Program of Works.

    With kind regards,

    Samer