Steel Structure construction schedule will depend on the design in particular bracing design. Usually there are two bracing designs; bracing by mean of concrete core(s), bracing by steel members spanning several floors. There is also a possibility of a combination of the two methods.
You shall look at the structural drawings and structural notes to find out if there are restrictions other than the usual.
Please note I am not adding "soft links" as to force resource leveling as I consider it bad practice even when over 90% of our schedulers do it, perhaps because of poor software or because of poor scheduling culture. In any case combining soft links with resource leveling is considered bad practice by most schedulers.
The following are two sample files that might need to be adjusted to actual design and structural requirements. Just to give you an idea on the level of detail I would use.
If braced by means of concrete core(s) formed and poured using slip forms, if no slip form is used then some extra links shall be added as to keep the core ahead but close to the steel structure for scaffolding.

If braced by means of steel bracing:

Usually concrete cannot be poured until the levels to be concreted are braced.

For the substructure I do not have enough detail but about the piles it might be you have to drive hundreds of piles. Therefore I would not go into the garnularity of scheduling the subactivities that go into the piling operation of each individual pile. I would keep it within the following breakdown of overlaped activities.

http://www.generalcontractor.com/resources/articles/empire-state-building.asp
The Empire State Building is a marvel of engineering and architecture, and it occupies a unique place in the history of construction companies and construction management. Not only was the 1453-foot, 103-story structure built in just over 13 months, the construction company that took on the daunting job allegedly began with nothing on hand - no equipment or supplies that would be sufficient for such an enormous undertaking. How they accomplished the task is a case study in early, successful commercial construction management.
Well, they did it with a slide rule, not with some modern CPM software, some notorious for their Bugs and installation problems. If it takes you more than 2 minutes to install or update your software you are using a tool that most probably is going to create more problems than scheduling with a slide rule.