Structural Steel Shed

Vrinda MMember for 18 years 4 months
Created
5
3
0
Can anybody mail me the sequence for a structural steel shed incorporating the MEP works???

Thanks,

Vrinda

5 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Vrinda,

    The word "Shed" must be a little bit elaborated in order to understand the size of the metal building that you are talking about. In essence, you will have the following sequence:

    I. Substructure
    Site Survey
    Exvacation
    Isolated Footing;
    Shuttering,
    Reinforcement,
    Anchor Bolts Placement
    Casting,
    Insulation,
    Instulation Protection
    Fill around footings
    Vapor Barried placement or Blinding
    Reinforcement
    Casting of Slab on Grade

    II. Superstructure Erection
    Columns and Rafters
    Purlins, Girts and Sag Rods
    Wire Mesh and Insulation
    Cladding
    Cranes if any
    Windows and Doors
    Trims and Accessories
    Gutters and Downspouts
    Mastic and Foams
    Fire Protection, Paint and specific requirement might be needed.

    III. Electromechanical
    Cable Trays and wiring
    Fire Fighting system
    Fire Alarm System
    There are over 15 E/M system and depending on the design that you have, you can include them.

    IV. Finishing
    you will need an office area, storage, electrical room, and toilers, this is usually made of Block. The sequence is straight forward.

    If you have any other question, or you need more detail information, please let us know.

    With kind regards,

    Samer
  2. 0
    Vrinda M ·
    Thanx a lot Samer.

    It was of gr8 help....

    Vrinda.
  3. 0
    Vrinda M ·
    Yes,forgot to write the area of this open shed is just 1300 sqm and two guard houses of 35sqm.

    Anyways thanx for ur help.If anythng will be tre thn will ask u.

    Vrinda.
  4. 0
    Mike Testro ·
    Hi Samer

    Another clear and comprehensive list of activities.

    Just one or two additions.

    Under slab drains and service trenches.

    Rainwater disposal.

    External works - roads and landscaping

    Don’t close the cladding until all big M&E kit is installed.

    Look out for Upstand roof lights along the ridge - they will need scaffold access up through the lower roof.

    Best regards

    Mike Testro
  5. 0
    Samer Zawaydeh ·
    Thank you Mike,

    I hope Viranda will make use of the information. Next time will make it more comprehensive and detailed.

    With kind regards,

    Samer