does anyone know the sequence of events when construction a Timber Framed building?

Regards,

J

4 replies

Oldest first
  1. 0
    John Banks ·
    I’ve got some MSP examples for residential timber kit if that’s any use?
  2. 0
    Mike Testro ·
    Hi James

    The usual sequence is.

    1. Fix and Level sole plates
    2. Install wall panels - line and level
    3. Fix floor cassettes
    Repeat 2 & 3 up to roof plate
    4. Fix roof plate
    5. Fix roof trusses.

    Best regards

    Mike Testro
  3. 0
    Samer Zawaydeh ·
    Dear James,

    The typical activities are :

    1) Substructure
    a. Excavation
    b. Foundation
    c. Foundation Insulation and Insulation Protection
    d. Fill
    e. Slab on grade
    2) Superstructure
    a. Main Frames
    b. Secondary Beams and Bracings
    c. Cladding
    d. Door and Windows
    e. Gutters and Downspouts.
    3) Electromechanical Works
    4) Finishes

    With kind regards,

    Samer
  4. 0
    Sham Dham ·

    Has anyone done a study on

    Has anyone done a study on installation rates for Cross Laminated Timber type of buildings

    And how much faster it is compared to tradinal build