Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems?

John ReevesMember for 13 years 5 months
Created
1
4
0

Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems? - These items are intertwined - one of the worst things you can do is make the schedule into either a submittal log (or a to do list).  But how to you efficiently feed the info between them - surely P6 has addressed this.  I think years ago they did with their Old CM tools (ie Expedition - yes I am old.) but by getting fancier I think that easy link was lost.  I only see them excel now days.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    the old expedition is not

    the old expedition is not Primivera Contract Manager and you can inport of there into excel.

    The other option is to build a submittal log yourself by using the p6 import spreadsheet

Log in or join to reply