Early and late S curves in P5.....

Martyn CoatesMember for 19 years 2 months
Created
1
1
0
I seem to be having a problem getting the curves from p5

I want the data in excel and want to show early and late curves like you can do in P3 for a project.

There seems to be remaining setting dates etc but I can not see any setting to give the whole hour spread from start to finish (whether actual or not) in the form of an early & late curve.

help

I havent seen any definative guide or help to anyone else in older posts

1 reply

Oldest first
  1. 0
    Nathaniel Alexander ·
    Martyn

    Try the following

    1)Report Wizard select Time Distribution Data Box
    2)Choose the report - Activity Resource & role assignments
    3) Select options
    4)Filter as follows - Where Open Status = open
    5) go to Time interval Fields and select
    --Remaining units - remaining early
    --Remaining Late units - Remaining late
    then next next till the report finishes

    Hopefully this will do the trick