progress against critical path

Mukunda YMember for 17 years 11 months
Created
5
2
0
is it possible to update the progress against the critical path activities? critical path keeps on changing...so how can update the planned versus actual only for critical path activities?
Thanks
Mukunda

5 replies

Oldest first
  1. 0
    Anoon Iimos ·
    try to create filter to show only the critical path, and then make updates
  2. 0
    Mukunda Y ·
    how it can be as critical path keeps on changing???
  3. 0
    Anoon Iimos ·
    critical path only changes once you make updates, just don’t forget to keep the baseline
  4. 0
    Mukunda Y ·
    is it practical? anybody measuring progress by this method?
  5. 0
    Samer Zawaydeh ·
    Dear Mukunda,

    The Schedule is a live document. The approved Schedule is your baseline. This is what you measure your progress against. You do not measure the progress against the critical path. Critical Path are activities with float zero or negative (later on).

    Each day the float on your activities decreases. So if you don’t complete the activity, and the float is gone, it becomes critical.

    With kind regards,

    Samer