Does any one have come across float mapping and how do they help in preparation of claims ?

2 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Shahul,

    I would recommend that you identify the time of the delay event, and the duration of it. Subsequently, find out the activities with equal float time to that duration. You delay event (in theory) should be studied on all these activities. Of course you have to take the constraints into consideration.

    Let me know how we can assist more.

    With kind regards,

    Samer
  2. 0
    Shah. HB ·
    Many thanks samer let me give a try and get back to this forum for further discussion