ACTUAL DATES IN REVISED PROGRAM
In the Open Standard
Kumar IMember for 23 years 3 months
- Created
- 6
- 3
0
Hello,
We have a baseline schedule with Project start date of 1-January-2009.The schedule has been updated regularly since then.Now the Program is to be revised as on 15-may-2010.If we update the schedule till 15-may-2010 with actual dates and run the schedule with date date of 15-may-2010 and do the required revision to the duration/logic of the activities,it is OK.
The Point we want to Clarify is it is acceptable to have a revised program with actual dates and data date not as per the contract start date.Or there should not be any actual dates and the data date should be project start date
We have a baseline schedule with Project start date of 1-January-2009.The schedule has been updated regularly since then.Now the Program is to be revised as on 15-may-2010.If we update the schedule till 15-may-2010 with actual dates and run the schedule with date date of 15-may-2010 and do the required revision to the duration/logic of the activities,it is OK.
The Point we want to Clarify is it is acceptable to have a revised program with actual dates and data date not as per the contract start date.Or there should not be any actual dates and the data date should be project start date
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?