Reason for the change FF>TF?

Shah. HBMember for 17 years 10 months
Created
3
2
0
Hi to all

I checked a schedule and i found for an activity FF [Free Float]
is greater than TF [Total Float] but in general FF lesser than Total float.

Is there any reason for the change in the condition?

3 replies

Oldest first
  1. 0
    Muhammad Anwar ·
    Shahul,

    If there is a must finish by constraint or mandatory finish pushing end earlier than what it should be will result in FF>TF. Check for the contraints and project finish date at project setting level.

    Hope this will solve the problem.

    regards

    Muhammad
  2. 0
    Umer Mehmood ·
    some times in this problem happen when you changed your calculation mode preference , especially when open ended activities are consider critical while scheduling

    Hope this will help

    Best REGARDS

    UMER MEHMOOD
    ABU DHABI
  3. 0
    Shah. HB ·

    Many thanks Umar & Anwar

    I got the solution for the raised query