Delay issue confusion
In the Open Standard
Tasnim YusoffMember for 16 years 3 months
- Created
- 2
- 4
0
HI,
I’m confused about the EOT programme. My client want to see impact for each event to overala programme.
I have few outstanding works which contributed to delay event for each level in my programme.
The works at each level start concurrently.
Inside the programma it is just have activiries for general installation for each floor. Which contractor can start the whole floor at the same time.
How to link the delay event to the activity afected as not the whole duration for that activity is impacted by that delay? The delay happened in between work progress and other works at that floor still can continue. That area will be on hold until we get comfirmation from the client.
I’m confused about the EOT programme. My client want to see impact for each event to overala programme.
I have few outstanding works which contributed to delay event for each level in my programme.
The works at each level start concurrently.
Inside the programma it is just have activiries for general installation for each floor. Which contractor can start the whole floor at the same time.
How to link the delay event to the activity afected as not the whole duration for that activity is impacted by that delay? The delay happened in between work progress and other works at that floor still can continue. That area will be on hold until we get comfirmation from the client.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?