Problem related to profile view layout

Shazia khanMember for 18 years 5 months
Created
1
2
0
Hi-all

Could any one advise how i can save profile view with s-curve in p6.

i have set timescale and profile view every thing while i save as a s-curve layout it was saved but i open it the picture was not same whati had save.

please advise

Thanks & best Regards

1 reply

Oldest first
  1. 0
    Daniel Limson ·
    Hi Shazia,

    I have encountered the same problem before, what I did was to save the profile in Adobe PDF file. Later on I found out that you need to save the layout so you can recall it back.

    Hope this helps,

    regards,
    Daniel