Layout import not working

Akhileshwar SharmaMember for 7 years 1 month
Created
4
4
0

Hi,

I imported a layout and used that on two projects, but its working on one of the projects and not on other.

I'm not able to use custom column like other and while rearrangement its not showing the imported items.

 

thanks,

4 replies

Oldest first
  1. 0
    Santosh Bhat ·

    If your layout uses activity

    If your layout uses activity codes or UDF fields then it will not work because they are referencing field ID's from a different database that wont exist in the destination database. You will have to rebuild this part of the layout manually.

  2. 0
    Zoltan Palffy ·

    if you have codes in that

    if you have codes in that layout it will only work with the project that the codes were created in. 

  3. 0
    Rafael Davila ·

    https://www.replicon.com/cust

  4. 0
    Akhileshwar Sharma ·

    Thanks

    Thanks