HI every body
i have a new project which is waste water treatment plant, any help by descriping how the elements work together ? any discription about how these plants work?

3 replies

Oldest first
  1. 0
    Gary Whitehead ·
    There are a number of different potential treatment options, so the below is fairly generic. Do you not have any kind of scope or spec to work with?

    -Screens & screenings handling plant (metal mesh to filter out major detritous which could harm pumps, etc. Screenings handling might be washing it & conveying to skips)
    -Stone / grit removal (eg constant velocity grit channels with dredging pump)
    -Inlet pumping station
    -Primary Settlement tanks (floating scum removed from the top, settled sludge removed from bottom via bellmouth)
    -Biological treatment –either
    a) Aeration lanes (settled sewerage passes through aerated channels seeded with bugs which eat biological matter)
    b) mineral beds (sewerage trickles through the packed mineral beds, with the bugs seeded on top)
    -Final Settlement Tanks (similar process to PSTs above)
    -Effluent outflow

    In addition, the sludge taken from PSTs and FSTs has it’s own process stream:
    Sludge storage tanks
    Sludge thickening / dewatering
    Then 1 or more of the following :
    a) anerobic digestion tanks, with gas being recovered as renewable energy
    b) Liming plant to reduce odour & raise ph
    c) Incineration
    d) Thermal drying (export to agriculture)
    e) Pasteurisation
    f) Thermal Hydrolysis


  2. 0
    Samer Zawaydeh ·
    Dear Rola,

    This is like any other project, you need to start with

    Material Submittals (civil, electrical, mechanical and maybe chemical)
    Engineering Drawings
    Procurement
    Construction
    Testing and Commissioning
    Handing Over

    What Gary is describing is the actual process. It is wounderful to be able to understand it in order to be able to monitor the construction and record the progress. Of course, you will be able to identify the Changes from design as well.

    Review the BOQs for the material, and the Issued For Construction drawings for the shop drawings to be prepared, and then sit with the Construction team to determine the sequence of construction.

    With kind regards,

    Samer
  3. 0
    Saeed Shaikh ·

    wysiwyg_imageupload::

    Please allow us to submit you small introduction of our company, products, Distributions and Services and etc. which might be you need to instaling west water plant projects.

    ASALI INTERNATIONALEngaged in Manufacturing, Business Development, Sales and Marketing, Supply and Solution etc. for our own products Flow meters, Capacitance Level Transmitters, Level Indicators, Valves, Strainers, and other engineering and mechanical products.

    Please find some copies of our new 2012 brochure and introduction in attachment, after your approval and confirmation I would like to have small business meeting with to submit you technical data of our products Flow Meters and etc as per your valuable orders and positive comments.

    Awaiting your prompt and positive response.Thanking you and best rgds.

    For  M/s. ASALI INTERNATIONAL.

    Flow meters & Industrial Products Manufacturing,

    Proprietor:-  SHAIKH SAEED.

    Contact details:-.

    Tel / Fax.+91 (022) 2741 6355

    Dir Line. +91 (022) 6565 6355

    Cell. +91 8108 55 63 55.

    Cell. +91 9768 920 924.

    email. asaliintl@asaliintl.com

    www.asaliintl.com

    Address:-

    OFFICE:- B-137 PLOT NO. J7-J9 KOHINUR INDUSTRIAL COMPLEX,TALOJA MIDC,NEW BOMBAY TALUKA PANVEL DIST. RAIGAD, PIN CODE. 410208,M.S. INDIA.

    FACTORY:- 39-40 RAUTARA INDUSTRIAL ESTATE, POST PADHLE, NEAR SHIL PHATA OCTRAI NAKA, MAHAPE MIDC MUMBRA THANE M.S. INDIA.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?