Dear Members

I need urgent advice on conversion procedures for conversion of my programme in MSP 2007 to Primavera P7.

I have tried many ways but failed to do successfull conversion.
 

Please advice what is the correct procedures to convert MSP 2007 to P7 

2 replies

Oldest first
  1. 0
    Daniel Limson ·

    MSP 2007 Conversion to Primavera P7

    Hi Vineet,

    Try importing it, it is not an exact conversion, but you can always delete the summary bars that you do not need.

    Regards

  2. 0
    Kamesh Avasarala ·

    Dear vineeth ,   the

    Dear vineeth ,

     

    the procedure is 1st you go to ms project and save as  that ms- project in XML format . and that can be easily import in primavera when you impotr you select import and selet msproject xml import option and do import . iam doing the same thing i easily doint that in same method.

     

    Kamesh