Import from MS Project 2007 to P6

John WilsonMember for 15 years 11 months
Created
14
4
0

Has anyone succesfully imported from MSP 2007 to P6. Each time I try I get an error message

14 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello John,it is just not

    Hello John,

    it is just not possible to import / export between Primavera PM6 and MS Project when you have MS Project 2007 / 2010 installed on the PC; you cannot import from MS Project 2003 either

    Alexandre

  2. 0
    Tanveer Ahmad Niazi ·

    Hi Mr. Alexandre you are

    Hi Mr. Alexandre

    you are right i also tried to import my subcontractors program to P6 but could done. but i didnt try it to import to P3 and then to P6, would that do the job?

    Tanveer

  3. 0
    John Wilson ·

    It appears that the only way

    It appears that the only way to do it is remove MSP 2007 / 10 from the machine and then install 2003

  4. 0
    Sandy Matheson ·

    Have yopu tried saving in MS

    Have yopu tried saving in MS Project as .xml file?  Should then be available for import?

  5. 0
    Tammy Pitcher ·

    Hi, I am trying to import

    Hi,

    I am trying to import from MSP 2007 to P6, I have saved the MSP file as .xml and then tried to import to P6 and I keep getting an event code CNFF\-3348-2. Maybe I am not importing it corecctly. Can anyone help me with this matter??? Please & thanks

  6. 0
    Tammy Pitcher ·

    what is the error mesage you

    what is the error mesage you are getting?

  7. 0
    Tom Robinson ·

    MS Project 2003

    MS Project 2003 (MPP) converts to P6 version 7 without any issues. in fact, its pretty seamless.

     

    -tom

  8. 0
    Andy Power ·

    P6 version 7 can export to

    P6 version 7 can export to MSProject XML 2007 so you should be able to import an XML created in MSP2007 in to P6v7.  Unfortunately I dont have MSP2007 to try this out, I can import XML from MSP 2010 with no issue.

  9. 0
    Sandy Matheson ·

    I tried my own suggestion,

    I tried my own suggestion, save as .xml file and it failed!  I got the same error message as Tammy.  I have been communicationg with Oracle on this for some weeks now and they seem to think it is relared to my Windows/Java set up.  I have made some changes as they suggested and got past the error event code.  But still it fails!  I get a message 'Process completed with errors' but no project created.  Any ideas?  Still working with Oracle but taking some time!  (I got round my original requirement by just coping in the activitivities and putting in the logic, thankfully a small and simple network!)

  10. 0
    Tammy Pitcher ·

    Hi Sandy, After some more

    Hi Sandy,

    After some more research I found out that it is a Java issue. I am just a user on the network so i forwarded what i found to my IT guy and he is working on it. if he figures it out I will find out what he did and relay that info to you. Sorry that I couldn't be of more help.

    I have set up a template in P6 so I just copy that and add or delete activities as necessary. It's easier than building the schedule from scratch.

  11. 0
    Tammy Pitcher ·

    Hi Sandy, After some more

    Hi Sandy,

    After some more research I found out that it is a Java issue. I am just a user on the network so i forwarded what i found to my IT guy and he is working on it. if he figures it out I will find out what he did and relay that info to you. Sorry that I couldn't be of more help.

    I have set up a template in P6 so I just copy that and add or delete activities as necessary. It's easier than building the schedule from scratch.

  12. 0
    Arend Kok ·

    Sorry Alexandre, but that is

    Sorry Alexandre, but that is simply not true.

     

    I have both 2007 and 2003 installed and my imports work perfectly fine.

     

    The trick is to open an mpp file with 2003 first (so it is the default handler for these files) and then do your import into Primavera.

     

    I cannot comment on having 2010 installed, although I cannot see that this wil create and issue.

     

  13. 0
    Emre Bayrak ·

    Hi,Any of you solved the

    Hi,

    Any of you solved the problrm, i have got the same error massage?

  14. 0
    Tammy Pitcher ·

    Hi All, If there are any

    Hi All,

    If there are any empty lines in your MSProject schedule P6 can not compute. So what I did was open the schedule in MSP and made sure there weren't any empty lines then saved the schedule as an .xml file and then the import was sucessful.

    Hope this helps.

Log in or join to reply