Vertical and Horizanta projects planning

Rola SabbahMember for 16 years 10 months
Created
1
1
0

Hi planning planet,

i have a question, what is the criterias taking into consideration while planning for horizantal and vertical projects?

for vertical projects such as towers, for example we consider that 60% of the project duration is for skeleton but for horizantal like factories less due to the presence of E/M fixes.

what other basic factors in planning do u professional planners do? i mean even before developing the project like setting out the major milestones in the project.

Thanks

1 reply

Oldest first
  1. 0
    Muhammad AQEEL ·

    One Day clander Issue...!

    URGENT!!!

    Dear All,

    I 'm facing a problem with clander like;

    One i give duration One day e.g: activity start on 12/10/2010 and will be finish on 12/10/2010 than this will be consider one right duration  But with me on the schedule date is comning 13/10/2010 instead on 12/10/2010 and showing the org. Duration is 1 (one). Can some one fix this problem. this will be much appriciated.

    Regards,

    maqeel

    (maqeel2008@hotmail.com)+966599981584

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?