Skip to content

One (1) Calendar Issue

Muhammad AQEELMember for 16 years
Created
0
1
0

URGENT!!!

Dear All,

I 'm facing a problem with clander like;

One i give duration One day e.g: activity start on 12/10/2010 and will be finish on 12/10/2010 than this will be consider one right duration  But with me on the schedule date is comning 13/10/2010 instead on 12/10/2010 and showing the org. Duration is 1 (one). Can some one fix this problem. this will be much appriciated.

Regards,

maqeel

(maqeel2008@hotmail.com)+966599981584

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?