One (1) day Calendar Issue
In the Open Standard
Muhammad AQEELMember for 16 years
- Created
- 1
- 3
0
URGENT!!!
Dear All,
I 'm facing a problem with clander like;
One i give duration One day e.g: activity start on 12/10/2010 and will be finish on 12/10/2010 than this will be consider one right duration But with me on the schedule date is comning 13/10/2010 instead on 12/10/2010 and showing the org. Duration is 1 (one). Can some one fix this problem. this will be much appriciated.
Regards,
maqeel
(maqeel2008@hotmail.com)+966599981584
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?