One (1) day Calendar Issue

Muhammad AQEELMember for 16 years
Created
1
3
0

URGENT!!!

Dear All,

I 'm facing a problem with clander like;

One i give duration One day e.g: activity start on 12/10/2010 and will be finish on 12/10/2010 than this will be consider one right duration  But with me on the schedule date is comning 13/10/2010 instead on 12/10/2010 and showing the org. Duration is 1 (one). Can some one fix this problem. this will be much appriciated.

Regards,

maqeel

(maqeel2008@hotmail.com)+966599981584

1 reply

Oldest first
  1. 0
    Ronald Winter ·

    P6 is not a day-oriented CPM

    P6 is not a day-oriented CPM software.  Activities are scheduled down to the minute.  To understand your issue, you will need to display hours and minutes as well as days.  Once you do, I am sure that the answer to your problem will be evident.  Good luck! 

Log in or join to reply