Revise,recover & Update

Hatem SmadiMember for 16 years
Created
1
2
0

Can Any body provide me  the difference between , Programme revision,recovery , Update ,, is it mentioned any where

in the PMI Books

1 reply

Oldest first
  1. 0
    Rizwan Rauf, PMP ·

    Hi,If your project got

    Hi,

    If your project got extension of time due to delays (by either parties), then, you will prepare revised programme/schedule.

    If your project got delayed and client is not agreeing for extension of time, then, you need to prepare & submit Recovery Program / schedule in order to recover/compensate your delays.

    Bi-weekly / Monthly progress updation in your schedule by putting actual dates & pecentage complete  is your programme update.

     

    Regards,

     

    Rizwan Rauf