Open a P5 file using P6

Margarita PapaioannouMember for 15 years 11 months
Created
1
3
0

I've been trying to open a P5 file into P6 I get the message: "A version 5 XER file cannot be imported."

Any ideas how can I open it?

Thank you!

1 reply

Oldest first
  1. 0
    Michael Ramos ·

    open xer file in notepad or

    open xer file in notepad or wordpad

    and change the 5.0.0 as 6.0.0

    save then you can now open it in p6