Importing P3 files to P6 V7

Mohamed YahiaMember for 14 years 5 months
Created
6
5
0

Hello Planners,

I have an issue importing P3 Files into P6.v7 in win 7 . When I go to file and choose import and check box to select project then press next this msg appear " an application event has been intercepted please note the event code for reference ECLUS-0337-4 and it appears for import any p3 files 

I’ve tried to import it but i can’t find the solve
Can anyone shed any light on why I cannot import these P3 files into P6?

 

Best Regards,

m.Yehia

6 replies

Oldest first
  1. 0
    Kamesh Avasarala ·

    hi if you can send me u r

    hi

    if you can send me u r file p3 file i can send you p6 file , it may be some prog error

  2. 0
    Mohamed Yahia ·

    Dear  Kamesh Thanks for your

    Dear  Kamesh

     

    Thanks for your attention , can you send me your email address

  3. 0
    Ronald Winter ·

    Mohamed,  Do you have P3

    Mohamed,

     Do you have P3 installed on the same machine that you are trying to import the “P3 Files”?  P6 now required P3 to be installed before you can do this.

     Just what do you mean when you say ‘P3 Files’; are you trying to import a .PRX file or are you trying to import a schedule directly from P3 (multiple .P3 files)?

  4. 0
    Muhammad Imran ·

    I'm facing the same problem.

    I'm facing the same problem. It was ok when P6 of Project Managemet installed but on converting to Oracle P6 Professional R8.3 (Standalone) this Error occurs.

    Can anyone give the proper solution of It?

    Regards 

    Muhammad Imran.

  5. 0
    Zoltan Palffy ·

    here are the instruction on

    here are the instruction on how to do this.

    You must have the p3 files in their uncompressed from to import into p6. If this is a 64 bit operating system then you wil not be able to uncpmress the files to thier native from unless you install windows virtaul xp 

     

    here my link and the instructions 

    http://pmsite.com/forums/viewthread/3146/

  6. 0
    Zoltan Palffy ·

    here are the instruction on

    here are the instruction on how to do this.

    You must have the p3 files in their uncompressed from to import into p6. If this is a 64 bit operating system then you wil not be able to uncpmress the files to thier native from unless you install windows virtaul xp 

     

    here my link and the instructions 

    http://pmsite.com/forums/viewthread/3146/