monthly cash flow for a WBS

Syed Faisal HashmiMember for 16 years 10 months
Created
4
5
0

Hello friends

 

Please help me to make monthly budget cash flow curve for the wbs. I prepared primavera p6 program in which i make wbs like sub structure work, structural work ground floor, structure work at first floor,structure work at Second floor,structure work at Third floor,...and on the same lines i make architectural works, Plumbing works, HVAC works, Fire Fighting Works, Electrical Works and so ..on. within each each wbs i gave the activities.

 

i load all the cost from BOQ against each activities..i can generate monthly cash flow from p6 reports.

 

now i need to make monthly cash report for particulat type of wbs.. like i need to have monthly cash flow for structural works, or fire fighting works..

 

please help me..

4 replies

Oldest first
  1. 0
    Michael Ramos ·

    you can copy paste from

    you can copy paste from activity spreadsheet summarized as wbs to excel

    just copy again the wbs and paste in first column of excel

  2. 0
    Rafael Davila ·

    You shall try with the

    WBS Cash Flow

    You shall try with the histograms; perhaps by highlighting the desired WBS you will be able to create your Graphical and Tabular Reports for the selected WBS only, in a similar way other software does. Even if you switch to a different WBS view, say by responsibility instead of by phase or by area, the reports from closed WBS shall still be valid.

    Regards,

    Rafael

  3. 0
    Rafael Davila ·

    As you can see by combining

    CF by Responsibility

    As you can see by combining Cost Components (Cost Accounts) and different WBS definitions (different group sets) you can get what you want, if you add Cost Centers then the possibilities will be multiplied not only on your histograms but also on your tabular reports.

    Try it this is a no brainer, you shall try it on P6 shall be as easy as 1-2-3.

    Regards,

    Rafael

  4. 0
    Syed Faisal Hashmi ·

    Thanks friends..

    Thanks friends..