How method used for calculated actual progress for blinding concrete ???
- Created
- 2
- 4
hello all, i wish you doing will in you work
my problem that i faced in m work that we are started casting blinding concrete in the site and they want from me to calculate the actual progress for blinding concrete to compare with planned progress there is two methods i know put i don't know which one i choose
1- First method is depend on take coordination from site that they casted and calculate the quantities from drawings based on coordination
2- Second method is depend on the quantity of concrete that casted in site
i don't what method i used ???
Best regards
2 replies
Oldest firstLog in or join to reply