P6 - Using the Global Change funciton to remove 'Actual' Dates'

Danny FitzgeraldMember for 17 years 10 months
Created
6
2
0

Hello Chaps

I need to remove all 'actuals' from the start and finish date columns. I wish to retain the previously designated actual dates so that they now become the schedule 'plan' dates.

 

Can this done using the global change function?

 

Thanks in advance

 

Dan

6 replies

Oldest first
  1. 0
    Haitham Khaireldin ·

    You can do the following:Make

    You can do the following:

    Make a Global Change function in the then pane with AS EQ " " and AF EQ " " and PCT EQ 0

    But you will face a problem, which is that you already have progressed activities which means that the data date has an advanced date over some/all activities. So if you followed the above cited instruction you will have your project unprogressed but not matching with the original dates. So you have to make a new file with a project start date same as your original file, copy all the activities from the original file and paste them in your new file then follow the above instruction.

    Note: Dont transfer the old calender in your new file as that will change the data date again. Create a new one

  2. 0
    Michael Ramos ·

    hi haithamwhy do you need to

    hi haitham

    why do you need to create a new file and then copy paste? can't you change the data date to original data date and run?

  3. 0
    Michael Ramos ·

    if Activity Status not equal

    if Activity Status not equal Not Started

    then Activity Status EQ Not started

    note:

    if you have resource units already progressed, make them zero first by global change or assignment columns

  4. 0
    Krishna Kumar ·

    Hi Danny,               Why

    Hi Danny,

                  Why can't we try to save it as second baseline as we do in P3, so that all the actual dates becomes as scheduled plan & then you remove all the actual dates. Jus try it.

     

    Regards,

    V S Krishna kumar

  5. 0
    Haitham Khaireldin ·

    Hi Michael,No you cant change

    Hi Michael,

    No you cant change the data date to an older one.

  6. 0
    Shareef Abdul Azeez ·

    Hi Danny , You can remove

    Hi Danny ,

     

    • You can remove progress of activities in a  programme, but to retain the Actual dates and the new Original Durations, you will have to change your links to bring those (Actual) dates on the  non progressed (Baseline programme).

     

     

    Best Regards

    Shareef A Azeez

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?