level of programmes

Ronron MartinezMember for 16 years 10 months
Created
2
3
0

Hi, Expert

please advise the type of level of programme and the detail.

REgard's

Ron

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ronron Level 1  Whole

    Hi Ronron

    Level 1  Whole Project

    Level 2  Zones or Sections

    Level 3  Workfront summaries under Level 2

    Level 4  Task Cascades for each workfront

    Level 5 Individual tasks

    This is based on the a work front with different trades being summarised underneath - Vertical planning

    Not All trades summarised with different work front descriptioons - Horizontal planning which is not ideal.

    Best regards

    Mike T.

  2. 0
    Rafael Davila ·

    Level (-2) All Owner Jobs (To

    Level (-2) All Owner Jobs (To the Owner "The mother of the Whole")
    Level (-1) Owner Jobs by Municipality
    Level 0 Individual Owner's Job
    Level 1 All Contractor's Portfolios
    Level 2 Individual Portfolios
    Level 3 Jobs By Continents
    Level 4 Jobs By Country
    Level 5 Jobs by Municipalities
    Level 6 .... whatever gets down your pants

    Level 10 Whole Project
    Level 11 Zones or Sections
    Level 12 Workfront summaries under Level 2
    Level 13 Task Cascades for each workfront
    Level 12 Individual tasks

    I see the pretentious of some to define a "Universal" self serving definition of levels quite stupid. It shall means different to many, depending on your needs.

    I use several WBS definitions for a single job, each with different levels, this complicates the above myopic vision.

    P.S. If negative float is not an erroneous concept I guess negative level is not.