Mile stone and float

Ganesan KarthikeyanMember for 17 years 5 months
Created
2
4
0

HI Friends,

There are some dicrpency with my main contractor's planner

the case is,

i said to main contractor's planner that you can use a total float of an activity when the finish milestone is with Zero float. My main contractor's planner is having total float in activity as well as in finish milestone also. i told them to follow early start/finish dates, which will lead to early finish of finish mile stone and if you follow late start/finish considering the total float of an activity, it will lead to late finish of finishmile stone (which has float)  . My contractor's planner said to me that he can use the total float and can delay the activity when the finish milestone with total float.

 

is main contractor's statment correct.? please clarify

 

2 replies

Oldest first
  1. 0
    Shareef Abdul Azeez ·

    First decide whether your

    First decide whether your project has one finish date or two finish dates???

     

     

  2. 0
    Shah. HB ·

    Hi   KarthikeyanAssuming that

    Hi   Karthikeyan

    Assuming that float you mentioned in this subject is total float 

    Please check the below link ,

     

    http://en.wikipedia.org/wiki/Float_(project_management)

    Regards

    Shahul

     

     