Gantt Chart Activity
In the Open Standard
Ammar AbbasMember for 15 years 7 months
- Created
- 1
- 4
0
I am a beginner at primavera, i need to know how one can change gantt chart to show one day activity occupying the whole duration, like in this example activity starts somewhere mind sunday and ends in mid Thursday, where as I want it to start from the end of Saturday (start of Sunday) and continue till the end of Thursday, so that it occupies 5 days instead of 4.25 days approximately.
hope i m making it clear for you.
awaiting a response
1 reply