Sut Down Projects

Amro AhmedMember for 17 years 9 months
Created
3
2
0

Dear All,

Anyone have sample for shutdown schedule?

Thanks

eng_amrelsaied@hotmail.com

3 replies

Oldest first
  1. 0
    Mufiz Sayed ·

    Shutdowns are usually for

    Shutdowns are usually for short duration and crop-up on short notice, usually breakdown.

    Kindly elobrate your job, like which process plant, which dicipline M/E/I.

     

  2. 0
    Amro Ahmed ·

    I know that but what i mean

    I know that but what i mean sample for shutdown schedule

  3. 0
    Mufiz Sayed ·

    Milestone - Plant

     

    Milestone - Plant Shutdown Management Process

    Milestone

    Phase

    Origin

    Area of Responsibility

    Time to Plant
    Shutdown Date

    Selection of S/D manager

    1

    Process

    Owner

     

    Turnover meeting

    1

    Process

    Outgoing S/D Manager

     

    Initial cost estimate

    1

    Process

    S/D Team

     

    Work breakdown structure

    1

    Process

    S/D Manager

     

    Cost Control Structure

    1

    Process

    Administration

     

    Organizational Breakdown Structure

    1

    Process

    S/D Team

     

    Work list cut-off date

    2

    Process

    S/D Team

     

    Support plans complete

    2

    Process

    Support plan rep

     

    Work Package complete

    2

    Process

    Planning

     

    Master Execution Sched complete

    3

    Process

    Scheduling

     

    Detailed cost estimate

    3

    Process

    S/D Manager

     

    Procurement of materials

    3

    Process

    Procurement

     

    Procurement of machinery

    3

    Process

    Procurement

     

    S/D Readiness Review Audit

    3

    Process

    S/D Team

     

    Plant feed-out

    4

    Process

    Operations

    0 months

    Plant feed-in

    4

    Process

    Operations

     

    Reports & documents complete

    5

    Process

    S/D Team

     

    Evaluate plant turnaround

    5

    Process

    S/D Team

     

    Postmortem meeting

    5

    Process

    S/D Manager

     

    S/D Summary report

    5

    Process

    S/D Manager

     

     

    An example of the milestones used for each Shutdown. Activites & Duration is unique to each S/D & processing plant.

    In S/D most owners do not allow enough time or resources in the strategic and detailed planning phases to plan properly for the execution phase. This is reflected by the variances between the budget and schedule estimates in the business plan, and the actual cost and schedule duration of the execution phase.