Insertion of comments in P6

Roopa MVMember for 15 years 10 months
Created
2
3
0

Hi All,

Could you throw some light on whether I can insert comments in any cells in P6 like we do in Excel?

Thanks in advance for your replies.

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Go to Enterprise, User

    Go to Enterprise, User Defined fields and create one called "Comments" with a text Data type

     

    There's also the notebook section of the activity details window, but you can't filter on that

  2. 0
    Roopa MV ·

    Thanks Gary for the prompt

    Thanks Gary for the prompt reply. Can we 'Wrap Text' the comments as I can see the text is continuing in a single line?