Baseline Comments Received
In the Open Standard
Radhakrishnan NairMember for 17 years 9 months
- Created
- 5
- 2
0
Baseline Comments.
Some of the comments for a baseline are listed below. Appreciate your comments.
1. Project Milestones. Is it compulsory to have successors to milestones.
2. Restriction of maximum duration for activities to 20 days. Some long lead items are 50 days or more. How to cut short. Any hard and fast rules.
3. Key Milestone Should have zero float.
4. Restriction / limit of total number of critical activities. Maximum % allowed in comparison to total number of activities.
Regards,
Krish