IDEAL LINK TYPE FOR SUBCONTRACTOR ACTIVITY AND CLEARANCE
In the Open Standard
Hemanth KumarMember for 23 years 11 months
- Created
- 2
- 5
0
100 Rooms in a floor
"paint works" activity starts after clearance from main contractor
each room clearance is expected in different days
The plan is a floorwised one, having one single bar for "paint works " for a floor
how to secify the clearance in the plan?
as a milstone ? as a bar ? what should be the relationships ??