Updating Actual Units and using curve to spread remaining units.

Doyin McarthurMember for 23 years
Created
0
7
0

I am using P6, Labour resources, Bell Shaped Curve and fixed Duration & Units to resource load my schedule however, I have now been given Actual spent hours to update some activities.  If I change Duration Type to Fixed to update actual, P6 does not spread my rremaining units.

Is there a way to update Actual units while forecasting my Remaining units.