Updating Actual Units and using curve to spread remaining units.
In the Open Standard
Doyin McarthurMember for 23 years
- Created
- 0
- 7
0
I am using P6, Labour resources, Bell Shaped Curve and fixed Duration & Units to resource load my schedule however, I have now been given Actual spent hours to update some activities. If I change Duration Type to Fixed to update actual, P6 does not spread my rremaining units.
Is there a way to update Actual units while forecasting my Remaining units.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?