Hi all

 

i m facing a problem in P6.

 

I prepared a schedule in P6 loaded with resources i.e Cost and est wt. but when i m updating this schedule it is showing actual value for next month also .

 

for example when i m updating till Apr-11 it is showing actual value for May also .

 

Please help me !

 

for referance please see snap shot

3 replies

Oldest first
  1. 0
    Ferdinand U. ·

    check this

    check this link

    http://www.planningplanet.com/forums/primavera-version-pm5-pm6/421689/actual-units-exceed-data-date

     

    one possible reason is calendar time affecting data date or actual dates

    also check your actual dates

  2. 0
    Muthukumaru Senthuran ·

    Please check the actual

    Please check the actual progress and data date in hours.

  3. 0
    Muthukumaru Senthuran ·

    Please check the actual

    Please check the actual progress and data date in hours.