Changing OD w/out automatically changing activity % complete

John Rovir FernandezMember for 15 years 5 months
Created
3
3
0

Hi All,

Im making a revised schedule and this is one of my problem. I want to change the Original duration without changing automatically the Activity % complete. these activities already started and there are already progress on it.
I'll appreciate any help you give me. Thanks.

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi John If you cannot just

    Hi John

    If you cannot just extend the end date of the uncompleted section then you may have to take off the progress - extend the durations and then add back the progress.

    Best regards

    Mike Testro

  2. 0
    Muthukumaru Senthuran ·

    Hi Jone;   Basically you are

    Hi Jone;

     

    Basically you are revising this duration due to inaccurate of the original planned duration, it means the started activity could not progress as you planned . Progress % and remaining durtion to be determined by you.

     

    Senthuran

  3. 0
    Echezonachukwu Obiekwe ·

    Hi John, It all depends on

    Hi John,

     

    It all depends on the kind of progress % complete type you are using, if it is duration % then it would be affected but if it is physical % complete then you can go ahead to input the correct original duration to reflect the obtainable duration. if you are using units %, it depends on the quantity of the job delivered for you to get the progress %.

    I will advice you to always use physical % complete type so as to give accurate progress on the job.

    Regards,

    Eche.