WBS Query

Julie PlantMember for 17 years 7 months
Created
3
2
0

Hi,

I have a schedule which currently is down to level 21, I have amended my data limits within user preferences in the WBS view, however, when I look in the activity view my colours stop at Level 20.  Does anyone know how I can add a colour to the level 21 within the activity view. 

It is taking my Project Name as a level 1 and could do with it being a Level 0 - Any ideas ??

 

Cheers

 

Julie

3 replies

Oldest first
  1. 0
    Daniel Limson ·

    Hi Julie, Go to Admin and

    Hi Julie,

    Go to Admin and then click "admin preference" go to 'data limits' and modify EPS/WBS limit. I think the default is 20.

    Regards,

    Daniel

  2. 0
    Julie Plant ·

    Hi Daniel I have done that,

    Hi Daniel

    I have done that, however, in the activity view you seem to run out of Colours for the WBS at level 20, just wanted to know if you can amend the colouring systems to add in colours from level 20 onwards.

    Cheers

  3. 0
    Daniel Limson ·

    Hi Julie, You can certainly

    Hi Julie,

    You can certainly modify the colour of your choice by clicking the icon "group / Sort" and click at the level you want to change. You can actually customize it according to your colour preference.

    Sorry for the late reply as I am quite busy with tendering works.

    Best regards,

    Daniel

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?