Query on Primaver Intermediate Schedule
- Created
- 2
- 8
Here's a professional LinkedIn post that clearly explains the problem and invites experienced Primavera P6 users to help.
I need some advice from experienced Primavera P6 users regarding an intermediate/status baseline workflow.
Scenario:
- Primavera P6 Professional v22 (Standalone)
- I work on the client side and receive a weekly contractor schedule as an XER.
- Since I don't update the contractor's schedule, I'm trying to use last week's schedule as a status baseline to measure this week's progress and forecast changes.
Objective:
Create a Week 29 status baseline (Data Date: 25-Jun-2026) so that I can compare it against Week 30 (Data Date: 09-Jul-2026), without modifying the contractor's logic or creating a new schedule.
Approach attempted:
I duplicated the Week 29 schedule and used Global Change to convert the schedule into a status baseline by setting:
- Completed Activities:
- Planned Start = Actual Start
- Planned Finish = Actual Finish
- In Progress Activities:
- Planned Start = Actual Start
- Planned Finish = Early Finish
- Not Started Activities:
- Planned Start = Early Start
- Planned Finish = Early Finish
The idea is to create a snapshot of the Week 29 status and then assign it as the baseline to the Week 30 schedule.
The problem:
For most completed activities, everything works as expected.
However, for about 302 completed activities:
- Planned Finish remains equal to Baseline Project Finish instead of changing to Actual Finish.
- When I test a single activity with Global Change, P6 returns:
"Planned Finish Date cannot be earlier than Planned Start Date."
Example:
- Status: Completed
- Activity Type: Task Dependent
- % Complete Type: Units
- No constraints
- Planned Start = 10-Jun-2025
- Planned Finish = 24-Jul-2025
- Actual Start = 10-Jun-2025
- Actual Finish = 26-Jun-2025
Since the Actual Finish is clearly later than the Planned Start, the validation message doesn't seem logical.
Questions:
- Has anyone experienced this behavior in Primavera P6 Professional v22?
- Is this a known limitation or bug with Global Change on Planned Finish for completed activities?
- Is there a better method to create an intermediate/status baseline from a received XER for weekly client-side schedule analysis?
My goal is to compare weekly contractor submissions accurately (forecast slippage, variance, and progress) without altering the contractor's original schedule.
Any insights or alternative workflows would be greatly appreciated.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?