Improved Planned Completion Date - NEC

Tony SewellMember for 16 years 1 month
Created
0
2
0

I have an issue at present whereby we have been working to a target programme for a while and have recently combined these dates with the Cl32 programme and therefore the P.C has come back by 11 weeks.

 

The programme went in for submission but has recently come back with a non accpetance, therefore the alast accepted programme has a P.C date +11 weeks compaired to this last submission (it is realistic to achieve this new completion date).

 

We have just receieved a PMI for additional works, if assessed under the last accpeted programme then the works can be accomodated to some extent and only cause a slight delay.

 

However if assessed under the new P.C date then it has a bigger impact. Therefore have i got a case to say that we feel we should assess under this new programme logic (-11 week P.C albeit programme is not accepted) or do I have to assess on accpeted programme logic.

 

The new P.C -11 week logic is quite different therefore the assessment on the accepted programme would be unrealistic. Or becuase the -11 weeks to P.C is not accpeted is PM within rights to use up available float still within the accpeted programme?

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?