Baseline & Completion programme

Anil VargheseMember for 12 years 7 months
Created
9
7
0

Gents;

Could you please advise me a valid contractual phrase refering FIDIC to protect the skin of myself.

Sceneraio1 : Approved baseline MEP Programme prepared based on floorwide single access.

Scenerio2: Due to tremendous delay in civil works - 209 calendar days as of 9 February 2016 (total duration for MEP installation completion = 217 calendar days). No complete access was given to any floor as per approved baseline.

Scenerio 3 : Civil contractor revised the access dates in zone wise and vertcally scattered manner. Intially 4 access dates changed to 4 zones x 4 access = 16 Access dates.

Scenerio 4: MEP contractor revised the programme; considering the last access is giving to zone 4 where main elecrical riser, electrical rooms and LV room located. Sequencing changed and durations of activities increased.

Question : Shall civil contractor can claim to use the duration of baseline in the revised MEP completion programme? In this moment baseline is valid benchmark to revise programme; since they changed their sequence in providing access for MEP works.

Thanks

Anil

9 replies

Oldest first
  1. 0
    Anil Varghese ·

    Please give some advise.

    Please give some advise. Please.
  2. 0
    Rafael Davila ·

    Contractual Baseline governs

    Contractual Baseline governs until a revision is mutually agreed between MEP and whoever contracted him, maybe a General Contractor, maybe a Contract Project Manager if a prime contractor and not a subcontractor.

    In any case the conditions are substantially different and there is a possibility this requires and increase in time and cost.

    It takes a woman 9 months to bear a child, nine women cannot bear a child in a month.

    Of course the contract shall provide for what to do in such circumstances, but in case of a substantial change a contractor or subcontractor can reject a one sided alternative such as a Change Directive.

    It is better if the parts get together and agree for a change in schedule, EOT and cost adjustments if applicable, rather than litigation.

    If someone else was late then this is the party that shall be assigned accountability. To use the MEP contractor as a scapegoat is wrong.

  3. 0
    Anil Varghese ·

    Thank you for the advice.

    Thank you for the advice.

  4. 0
    Mike Testro ·

    Hi AnilOn a practical level a

    Hi Anil

    On a practical level a lot depends on whether the delays to the Civil Contractor can be passed up to the Employer or are they wholly the Contractor's problem.

    If the former thenit is best to collaborate and share the gains.

    If not then you will have a fight with the contractor.

    On the face of what you describe you have a sound case - not just for EoT but prolongation costs and disruption.

    You mention FIDIC - are you engaged on the sub-contract form?

    Best regards

    Mike T.

    PS I am moving your thread to the Forensic topic - you will get a better response.

  5. 0
    Anil Varghese ·

    Thank you Dear Mike.It is

    Thank you Dear Mike.

    It is purely a delay from civil contractor (Main contractor). We are nominated MEP contractor; though in terms of sub-contractor under main contract.

    As per contract; we are submitting detailed delay particulars in weekly basis. Till now; they were not issued an EOT in black and white. Moreover they issued a revised access date as said before.

    Thank you for your feedback and expecting more after case study.  

  6. 0
    Mike Testro ·

    Hi AnilThings to consider.1.

    Hi Anil

    Things to consider.

    1. Are you a nominated sub contractor under the FiDIC conditions or an "instructed" "named" sub contractor?

        If the former then you are in a much stronger position because the Employer will pay your claim and deduct the money from the Contractor.

    2. Is your baseline programme a binding sub contract document?

        If yes then the Contractor is in breach of contract and different rules apply.

    Best regards

    Mike Testro

  7. 0
    Anil Varghese ·

    Thank you Mr. Mike;Yes, we

    Thank you Mr. Mike;

    Yes, we are nominated Sub-contractor and the contract binds with access dates for MEP installation in each floor. Based on this access dates; we prepared and submitted MEP installation programme and Civil conrtactor approved and all other parties agreed.

  8. 0
    Mike Testro ·

    Hi AnilIf your access dates

    Hi Anil

    If your access dates are bound into the Sub Contract then any change imposed by the contractor is a breach of contract.

    You are not in an EoT situation at all.

    The contractor is bound to pay for all loss and expence caused by his breach of contract - it is as simple as that.

    Best regards

    Mike T.

  9. 0
    Anil Varghese ·

    Thank you Mr. Mike

    Thank you Mr. Mike