Hi,
I am Faiz.have been working for last two years as Planning Engineer Using Primavera V6.
I needed to ask that when I want show a activity on hold how to show it precisely.I tell you my procedure and you tell me that wither it is right or not??
I have an activity named "Mobilization"
The Planned Start is was 11th june 2011..and it started on the planned date i.e, 11th june 2011,
But it was holded due to some reason on 15th june and will remain holded till 18th june.
So I Started the activity..then entered the date of suspension and also the date of resumption.
is it Right??????But in bar chart it delays the activity not showing any different color for the suspended period...how to show it in the bar chart or activity table???
regards,