HI Gentlemen,

I have been updating the progress in primavers  version 6, by using Duration as % complete type.But i have also heard that one should use Physical as % complete type...I then used physical but the results were the same.Can someone tell me that what is the difference in using these two?????

 

Regards,

1 reply

Oldest first
  1. 0
    Hilal Hallani ·

    Physical % complete is

    Physical % complete is entered by the user and it implies that when percent complete would not be an accurate measure of real work performed or remaining. Where % complete can be entered by the user or the programme, this is not a real measure.

    Physical % complete is preferred over % complete in construction projects where speed of doing the work in activities does not remain same during the activity duration.

     

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?