   guys i have 5 identical schools and i want to copy the activities and assign new WBs for each but i had no filter for no activities such as P3 which i copy and paste with the same time change the activity IDs, how to do this in P6.

 

 

      thanks a lot.

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    Just copy the WBS of the

    Just copy the WBS of the first school.

    When you paste the copy back into the parent WBS, it will give you an option to copy the activities as well