Skip to content

Barrel Vaulted Timber Diagrid Roof Construction

Andrew PearceMember for 25 years 4 months
Created
3
5
0

I am currently undertaking a project that incorportaes a Glulam Timber Diagrid Barrel Vaulted Roof.

Has anyone here had any experience of such a form of construction that they would be willing to pass on.

The arch spans approx 38M and maed up of 4m grid primary members. These Glulam members being 585X160mm

This strucure is supported on a series of structural steel columns and braces but giving a claer span.

I can understand how it could be erected and looks as though a degree of off site modularisation could be achieved. Would be interesting to gain knowledge from anyone with first hand experience, lesson learnt etc.

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Andrew The best advice I

    Hi Andrew

    The best advice I can give you is to rely on the expert fabricators and erectors - this is very specialised work.

    As with all space frame roofs the key is the falsework support system - be prepared for the designed drop when the support is removed.

    Then the covering - it may be that the roof is not stabilised until the upper skin is fixed.

    Temperature expansion should not be a factor as with steel or aluminium frames.

    It will be impractical to plan for any work at lower levels until the falsework is finally removed and that won't be until M&E and finishing work in the roof zone is complete.

    Lets see if the LinkedIn guys give you any better adviice.

    Best regards

    Mike Testro

  2. 0
    Andrew Pearce ·

    Thanks Mike, That was my

    Thanks Mike,

    That was my thinking anyway, although a design manager in the office started whittling on about modularisation and trying to build with falsework. (Non starter I think)

  3. 0
    Mike Testro ·

    Hi Andrew Roman civil

    Hi Andrew

    Roman civil engineers knew how to build a stone arch without falsework support.

    They anchored each stone back to the previous third stone with iron rods and then dropped in the keystone - then took out the rods for the next one.

    Maybe our technology is not so advanced.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?