Appreciate your help on this one....I am getting the following error when trying to update the Baseline with Current Actviity changes for the period...
| 2011-08-04T16:20:50 | SEVERE | Errors located: RemainingDuration: Remaining Duration cannot be greater than At Completion Duration. |
I have reviewed all activities, no where is the RD greater than the At Completion Duration???
Any suggestions about what settings is required for updating Baselines??
Much appreciated...
Craig