% weightage calculation
In the Open Standard
Mohd AnjumMember for 15 years 8 months
- Created
- 3
- 1
0
Could anyone confirm me regarding the % weightage calculation.
i heard from some planner that you can calculate % weightage based on duration assigned for the activities to prepare s curve and track progress. Does it works sometime?
According to me for construction % weightage should be calculated based on planned labour unit and accordingly you can plot the s curve and track the progres.
waiting to hear soon from all u gr8 planners.