Skip to content

Planned% percentage Complete

Sajid SyedMember for 18 years 8 months
Created
1
1
0

Hi,

can some one comment on how to display  "Baseline % Complete" for activities as well as being summed up for the WBS levels as well.

the project is currently 50% into progress and "scheduled % complete"  values are not the same as the ones that i had initially calculated for the scurve from baseline.

Schedule%complete gives rescheduled values not the baseline values as i understand????

 

 

Regards

 

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Sajid What software are

    Hi Sajid

    What software are you using?

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?