issues with taking over an incomplete schedule
In the Open Standard
Danya PearceMember for 22 years 3 months
- Created
- 12
- 4
0
Hi All,
I am taking over a construction schedule which is incomplete (earthworks, some civils, structural and E&I has been scheduled) but certain areas need additional civil, structural and E&I and piping needs to be added overall. I still need to add in commissioning as well to the schedule.
The problem is that the work is progressing and I need to track this and add in the additional work. What is the best way to show both progress against the existing work in the schedule and at the same time add in the other work?
?????
Thanks
Danya
I am taking over a construction schedule which is incomplete (earthworks, some civils, structural and E&I has been scheduled) but certain areas need additional civil, structural and E&I and piping needs to be added overall. I still need to add in commissioning as well to the schedule.
The problem is that the work is progressing and I need to track this and add in the additional work. What is the best way to show both progress against the existing work in the schedule and at the same time add in the other work?
?????
Thanks
Danya
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?