Accepted Programme
- Created
- 5
- 4
I have just had a programme accepted by PM but it is qualified with various wording, one being that a certain activity should link to planned Completion (I should mention that the PM has instructed that works not affecting the opening of the scheme can be de-linked from Planned Completion and completed after - i.e fencing / not convinced he is entitled to do this but we have gone with it as we still get same pre lims).
my problem is that a new Cl32 has been accepted but he says accepted with a load of qualifications, when really he should have just rejected it stating his reasons and asking for it to be resubmitted, so when i save as Cl62 to assess PMIs against what do i assess....
1 - Use the Cl32 PM accepted and make changes as he suggested - however every acceptance he has qualified, which i have told him he cant, but he is the PM so he can do what he likes, therefore I dont want to change lasted Cl32 to reflect his quals as then I am technically accpeting all previous qualififcations.
2 - Use the Accepted Cl32 as it was submitted and ignore his qualifications.
3 - use the previous accepted programme and make it clear to PM that he cannot qualify the Cl32 and therefore we can only assume it is not accepted. (or just leave it as accepted but assess PMIs against the previous accepted.
any Help would be appreciated
Thanks
Tony
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?