Filtering By Responsible manager

AB TimoMember for 15 years 3 months
Created
3
2
0

Hello All,

I have been working on a Plan for Railway Track Construction and There are Separate Resposible managers for Each WBS.I want to Filter my Plan so that i give Each Responsible manger a list of activities that he is Responsible for.For this I Created a filter by Responsibly manager and applied it,the Issue is that,

* My Plan is filtered by that responsible manager but at the same time Other WBS Headings are Still Present in the activity table (Only WBS Name Not ts Activities). I want to Show the Required activities and WBS Name only.

* I know I can Generate Reports But the Requirement is not for the reports rather it is for the Activities with the bar chart.

I hope you all understand what i meant to say,

 

Best Regards,

Faiz

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Faiz,   It would help to know

    Faiz,

     

    It would help to know which software you are using...

  2. 0
    AB Timo ·

    Gary,I am Using Primavera

    Gary,

    I am Using Primavera P6

     

    Regards

  3. 0
    Gary Whitehead ·

    Go to View > Group and Sort,

    Go to View > Group and Sort, and tick the "Hide if Empty" box.

Log in or join to reply